Qatar seeking bids for Mesaieed aggregate port

Project involves building a four-lane conveyor system, six 25km stacker lines and an internal stockyard road network

Companies have been invited by the Qatar Primary Materials Company to bid for the contract to build aggregate berths at Mesaieed port.

A report by MEED said the engineering, procurement and construction (EPC) deal includes all the detailed engineering, design and construction of the facility, which will be built at the Mesaieed Gabbro Berths.

The project involves building a four-lane conveyor system with a 4,000 tonne an hour (t/h) capacity for each lane, six 25km-long stacker lines, each with a capacity of 4,000 t/h, three fixed hoppers that can discharge 200 t/h to trucks on a conveyor, a material switching system that allows material from any conveyor to be fed to any stacker, and an internal stockyard road network and 12 truck-weighing systems at the exit of the stockyard.

Advertisement

The company set September 17 as the deadline to receive the bids.

Add a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Keep Up to Date with the Most Important News

By pressing the Subscribe button, you confirm that you have read and are agreeing to our Privacy Policy and Terms of Use
Advertisement