DEWA: Water pumping station construction works at MBR Solar Park nearly complete

The project as well as others are being undertaken based on demand forecasts in Dubai running to 2030

Construction works at the water pumping station at the Mohammed bin Rashid Al Maktoum Solar Park stands at 92% complete, the Dubai Electricity and Water Authority (DEWA) has announced. The project is being implemented in two phases with Phase 1 boasting a total capacity of 4.5m imperial gallons of water per day (MIGD) and the second with a capacity of three MIGD.

“The 7.5 MIGD pumping station at the Mohammed bin Rashid Al Maktoum Solar Park uses the latest world-class technologies as well as energy efficiency. With work in full swing, it is expected to be completed and connected to Dubai’s water network by the end of June. The total cost of the project is $6.2m,” explained Saeed Mohammed Al Tayer, MD & CEO of DEWA.

Similar water network projects were being developed across all areas of Dubai to meet the rapid growth and keep up with the growing demand for water in all areas of the emirate through specific and reliable planning processes that are based on the latest foresight tools, Al Tayer pointed out.

Advertisement

He stated, “Electricity and water infrastructure expansion plans are developed based on demand forecast in Dubai until 2030.”

Abdullah Obaidullah, EVP (Water & Civil) at DEWA said the pumping station aims to meet the water demand of the different facilities and buildings at the Mohammed bin Rashid Al Maktoum Solar Park and nearby areas. The station will use clean energy from the solar park and can be operated remotely through the supervisory control and data acquisition system, he concluded.

Add a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Keep Up to Date with the Most Important News

By pressing the Subscribe button, you confirm that you have read and are agreeing to our Privacy Policy and Terms of Use
Advertisement